Bloemfontein Central Park Shopping Centre

Very tight access piling, as close as 30cm from existing column, with limited headroom of 2.5m in places.  28 end-bearing piles were installed to depths between 8-10m in only two days on site.

Piles were installed with a safe working load of 450kN